Pitch in a spiral reinforcing is a measure of:

Explanation:
Pitch in a spiral reinforcement is the axial spacing between successive turns of the spiral. It tells you how far apart each wrap is along the length of the member, not the thickness of the bar, the total amount of reinforcing, or how deeply the bar is embedded. A tighter spiral (smaller pitch) increases confinement and improves shear resistance, while a looser spiral (larger pitch) does the opposite. So the pitch is specifically the distance from one turn to the next along the length.

Pitch in a spiral reinforcement is the axial spacing between successive turns of the spiral. It tells you how far apart each wrap is along the length of the member, not the thickness of the bar, the total amount of reinforcing, or how deeply the bar is embedded. A tighter spiral (smaller pitch) increases confinement and improves shear resistance, while a looser spiral (larger pitch) does the opposite. So the pitch is specifically the distance from one turn to the next along the length.

Subscribe

Get the latest from Passetra

You can unsubscribe at any time. Read our privacy policy